Sand Preload Placement in Segment 4 Golden Ears Bridge
Owner: Bilfinger Berger Canada Inc.
$ 1,129,200.00
January 14, 2008 - April 15, 2008
The Segment 4 Sand Preload project is a (separate) component of work on the Golden Ears Crossing project in Maple Ridge. This section is located just north of the north bridge landing (and south of Lougheed). JJM continues to be a subcontractor to Bilfinger Berger Canada. The work consists of sand load / haul / place to construct pre-loads to various future road alignments, as well as some preload removal work, storm drainage installation, and limited grading work. This is high production materials handling with an aggregate sand quantity of over 150,000m3 to be moved in a short duration.
Project Contacts:
Matt Buechler, Project Manager
Ahmet Sezen, Project Superintendent
This project is complete. |